Voltage Drop Calculation Based on National Electrical Code

Calculating voltage drop is very important in every electrical design especially when we are dealing with sensitive loads. Failure to calculate the voltage drop properly will result to under-voltage at the receiving end of the system. And undervoltage could lead into inefficient performance of our equipments.

The National Electrical Code (NEC) provide basic method in calculating voltage drop in the system. This code provides data of standard conductor properties that can be used in voltage drop calculation.

Voltage drop formula:


  • Vd = ( 2 x Z x I x L )/ 1000 ---> for single phase system
  • Vd = ( 1.73 x Z x I x L) / 1000 ---> for three phase system

where:

Vd = voltage drop
Z =  impedance of the conductor per 1000 ft. (see NEC chapter 9 table 8 or 9)
I = load current in amperes
L = length in feet
1000 = constant to compensate with "per 1000 ft" in impedance value.

The National Electrical Code chapter 9 provides conductor properties based on 75 deg.C installations. Therefore for installations higher than above mentioned value we are required to consider special calculation procedure which is to be discuss in other article.

Table 8 refers to direct current system while  table 9 refers to alternating current system. But there are important considerations in using this NEC table 8 and 9, viz:
  • Use Table 8 for conductor sizes up to #4/0 since in this sizes R is approximately equal to Z
  • Use Table 9 for conductor sizes higher that #4/0
NEC Chapter 9 Table 9

Example:

A 10 HP motor is to be installed in a 220 V, 3-phase AC system. If the motor is located at 300 feet from the source, calculate its voltage drop?


Solution:

There are three approach in getting the current drawn of any motor.
  • Nameplate Rating
  • NEC given value
  • Conventional Calculation
The standard rule for getting the current rating of the motor is to know its nameplate rating. However if we are still in the design stage and we dont have any idea as to the exact specs of the motor then we will proceed to the NEC since the NEC provides the safest and optimum value of the motor FLA. And if we do not have the access to both of the preceding methods then we will do the conventional calculation as described in my other article "How to Prepare Schedule of Loads".

For the sake of discussion we will take the third method by assuming power factor and efficiency of the motor to be 80%.

I = (20 HP x 745 W) / (1.73 x 220 x 0.80 x 0.80)
I = 61.25 Amperes ---> full load ampres (FLA)

NEC provides that the the conductor must not be lesser than 125% of the motor's FLA.
  • Therefore: I = 56.0 x 1.25 = 76.6 Amperes
  • NEC table of conductor ampacities provides that at 76.6 amperes wire size must be #4 copper based on NEC Art 310
This value, 76.6 amperes will the basis of our voltage drop calculation.

note: the voltage drop calculation should be taken after we get the 125% safety factor provided by the NEC.

It follows that,

Vd= (1.73 x Z of #4 x 76.6 x 300 ft. )/ 1000


Based on NEC Chapter 9 Table 9,

  • Z = 0.321 ohm/ 1000 ft
  • Therefore: Vd = (1.73 x 0.321 x 76.6 x 300) /1000
  • Vd = 12.76 Volts

It follows that, %Vd = 12.76 V / 240 V = 5.3%

The NEC recommends that 5% voltage drop percentage is allowable in any circuit installation so if we strictly follow this recommendation then we will not accept #4 conductor but rather we will move up to the next higher size.

8 comments:

  1. Furthermore, by varying the current setting and the restraint on the movable element, Used Lab Equipment Distributors

    ReplyDelete
  2. ...and the 10 HP motor in the problem statement somehow turns in to a 20HP motor. It don't hurt to revise your work before publishing

    ReplyDelete
  3. The size of the branch circuit protection for motor loads shall not be greater than 250% of motor full load current for CB and 300% for non-time delay fuses on full voltage starting. CCTV Installers Melbourne

    ReplyDelete
  4. the voltage at each heap might be not exactly expected because of current move through the basic impedances (R, for example, the test leads and follow obstruction. high voltage resistor manufacturer

    ReplyDelete
  5. Be that as it may, the Farad all alone is a very enormous unit so sub-units of the Farad are generally utilized like miniature farads (uF), nano-farads (nF) and pico-farads (pF) to mean a capacitors esteem.
    China mosfet manufacturer

    ReplyDelete
  6. The purpose of the National Electrical Code is the practical safeguarding of persons and property from hazards arising by the use of electricity. about us

    ReplyDelete
  7. Decreasing conductor temperature. Allowable Voltage Drop According to the NEC, 2011 Edition. contact us

    ReplyDelete

Select Topics

electric protection Electrical Design power system protection Electrical Safety Fault Analysis Electrical Machines protective relaying circuit breaker electrical protection Electrical Equipment Technical Topics Electrical Installation BS7671 Power System short circuit analysis power system analysis what Earthing System Transformer DC Circuit Generator IEC standard Manual Resources Transmission Lines Unbalanced Fault Analysis electrical testing tutorial video Energy Efficiency ebook electrical motor how substation automation symmetrical components AC Machines Advance Circuit Theory IEC 60364 Renewable Energy Voltage Drop Calculation current transformer grid automation power system automation schneider electric smart grid Circuit Analysis electrical grounding fuse generator protection motor control power system stability quiz switchboard transformer protection ABB Manuals AC Circuit Busbar DC Machines Direct Current System GE Whitepapers Line to Line Fault National Electrical Code arc flash earth fault loop impedance electric vehicle electrical wiring power plant power system operation selective coordination switchgear video tutorial 3D printing AREVA AUS/NZ 3000 Assignment help Busway Current Nomenclatures Electricity Spot Market General Electric IEEE C37.2 IEEE/ANSI Device Numbers MiCom NFPA 70E Philippine Electrical Code Terms of use Theoretical ampacity battery building wiring capacitor circuit breaker curve cooling system cooper bussman disruptive technologies electrical earthing electrical harmonics energy industry engineering education iec 61850 inspection checklist learning protective bonding single line to ground fault transmission line protection voltage compensation voltage transformer voltage unbalance